Congratulations to Spencer, Paddy, Jason and the Nu Line Team for handover of the £500K Phase 3 Car Park for Diageo today. Well done to all for delivering the live site project incident free, ahead of programme, on budget.
The reconstructed zone provides parking for 76 visitor and employee vehicles, and is a critical phase of the ongoing Operation Opaque upgrade project at the Marshall’s Road, Belfast Plant. The Car Park follows the construction of the 17 vehicle Lorry Park completed in April, and precedes the upcoming phases of external area rejuvenation. The 'Live Site' works are being delivered by Nu Line for Diageo PLC, as part of the ongoing investment programme in the country’s busiest bottling plant.

Preparation Works for Lorry Park 200m3 Concrete Slab – April 2019

Phase III Car Park for 76 Vehicles – June 2019